Full IT landscape analysis and target architecture for 9,000 systems across 110 capabilities.
Period
Phase I: 03/2024 – 04/2025 · Phase II: 04/2025 – 05/2026
Effort
Phase I: 400 PT · Phase II in flight
Team
Core team of 15 (incl. 4 Aventario); 200 people across 110 sub-projects
Global pharma group. Approximately 110 departments newly created or restructured by a predecessor program. A high-fidelity view of the existing IT landscape — and a path to a target architecture — was needed across all of them.
Map and assess 9,000 systems across 110 capabilities, define IT system standards per (sub-)capability, develop a roadmap to the target landscape, and put in place a governance handbook for continuous evolution. Negative sentiment carried over from a predecessor project had to be turned around.
Phase I delivered and signed off. Full landscape analysis completed, target architecture and IT standards defined, roadmap and governance handbook in place. Phase II in delivery.